Anglesea Power Station
Coordinates:-38.389°N 144.1806°W
Country:Australia
Location:Anglesea, Victoria
Status:Closed
Commissioned:20 March 1969
Decommissioned:31 August 2015
Operator:Alcoa
Th Fuel Primary:Brown coal
Ps Units Operational:1 ×

The Anglesea Power Station was a brown coalpowered thermal power station located at Anglesea, in Victoria, Australia. The station had one steam turbine, with a capacity of . It was operated by Alcoa of Australia and supplied almost 40% of the electricity used by the company's Point Henry aluminium smelter, until the smelter's closure in August 2014.

The power station was brought online on 20 March 1969,[1] and was supplied with brown coal from the adjacent open cut mine, transported to the power station along a 3km (02miles)-long private road. Overburden was stripped and backfilled into the mined area by earthmoving contractors, using conventional power shovels and trucks. About 80 people worked at the mine and power station.[2]

In June 2015, Alcoa announced that the power plant and mine would close at the end of August 2015, after the company was unable to find a buyer for the power station.[3] On 31 August 2015, the plant ceased operation as planned.[4] Mine rehabilitation, and plant decommissioning and demolition, have been carried out.

History

In about 1955, test bores for coal were made at Anglesea by Roche Brothers, who were then operating a coal mine at nearby Wensleydale, where the reserves were dwindling. An extensive coal deposit was found two kilometres to the north of the Anglesea township, and mining commenced in 1959 to supply brown coal to industry and institutions in the Geelong area.

The mining rights were taken over by Western Mining Corporation (WMC) in 1961 to supply the power station planned by Alcoa of Australia. The Mines (Aluminum Agreement) Act of 1961 granted Alcoa a 50year exclusive right to explore and mine over some of leasehold land in the region.[5] After further drilling investigation, WMC relocated the mining operation to the east of the original mine, closer to the power station site and providing access to a larger coal reserve of 50e6LT. The total thickness of the coal seams is about, with total economic mineable reserves estimated at 70e6LT in the upper seam, and a further 90e6LT in lower seams. In 1992, the overburden to coal ratio averaged around 2.5 to 1, with an average coal thickness of .

Following negotiation with the Victorian government in 2011, Alcoa took up a 50-year extension of the Agreement under the Mines (Aluminium Agreement) Act 1961, allowing for continued operation of the mine and power station until 2016.[6] Alcoa outlined plans to expand the footprint of the mine by approximately 50 percent, taking the total disturbed area from approximately 400to, from about 2016.[7]

, approximately 35e6t of coal had been mined, with about 1.1e6t of brown coal being extracted annually to feed the power station that consumed of pulverised brown coal an hour. The coal at Anglesea has a high quality heat value when compared to other brown coals used to produce electricity in Victoria, but has a much higher level of sulphur, at around 3%, resulting in high levels of sulfur dioxide (SO2) being emitted.[8] Carbon Monitoring for Action estimated that the power station emitted 1.21e6t of greenhouse gases each year as a result of burning the coal.[9] The Anglesea power station drew its cooling water from six sub-artesian well bores, supplemented with rainwater.

With the closure of the Point Henry Aluminium smelter, Alcoa applied for and was granted a licence in May 2014 by the Victorian Essential Services Commission to sell electricity to the national electricity market. In February 2014, an Alcoa spokesperson said that it was seeking sale options for the power station, which might be closed if a sale was not possible.[2] In May 2015, Alcoa announced that it was unable to find a buyer for the plant, and would close it and the associated coal mine in August 2015. Closure occurred as planned on 31 August 2015.

Criticism

Since 2011, Alcoa and the Anglesea power station had come under increasing local criticism, with residents forming the Surf Coast Air Action group concerned with health impacts of air pollution from the mine and power station.[10] The group campaigned for reduced emissions from the power station and, following the closure of the Point Henry aluminium smelter, claimed that there was little justification for continuing the operation of the power station.[11]

Alcoa rejected claims it had exceeded targets, saying it had met its worldwide targets for reducing sulphur dioxide emissions, although it did not dispute that Anglesea's SO2 emissions actually went up from a base figure of to in 2012-13.[12] [13]

In a December 2013 submission to the Essential Services Commission, Friends of the Earth Australia argued that Alcoa should not be granted a licence to directly sell power to the National Electricity Market for four reasons: no additional coal-fired power was needed, Alcoa has no social licence to operate in the energy market, local health concerns, and that continuing operation of the power station undermined efforts to tackle climate change.[14]

Alcoa's licence to supply electricity to the grid was approved, although community groups said the decision lacked transparency and legitimacy, because no community consultation had been conducted by the Essential Services Commission.[15]

Protests

Two major protests in Anglesea occurred in 2014 regarding the future of the coal mine and power station. In July, over 500 people made up a human sign on the Anglesea beach saying "Shut it Down".[16] On 10 August 2014, several hundred people attended a rally and march calling for the coal mine and power station to be closed.[17]

See also

External links

Notes and References

  1. Book: Arklay . R. . Sayers . I. . Geelong's electric power supply : a history . 1970 . Gordon Institute of Technology.
  2. Murphy, Noel, 20 February 2014, 80 jobs in doubt at Alcoa’s Anglesea power station , The Independent, Retrieved 28 August 2014
  3. News: Alcoa to close Anglesea power station, coal mine after failing to find buyer. 12 May 2015. ABC News. 12 May 2015.
  4. Web site: Alcoa in Australia: News: News From Australia: Anglesea power station closes. www.alcoa.com. 27 December 2015.
  5. Web site: Anglesea Brown Coal Mine . Page 45 . Coal Mining Heritage Study . Vines, Jack . 2008 . heritage.vic.gov.au . 7 March 2010 . dead . https://web.archive.org/web/20091018070702/http://www.heritage.vic.gov.au/Publications/Typological-studies/Mining.aspx . 18 October 2009 .
  6. Soames, Nicholas, 25 October 2011, Alcoa Anglesea Mine Agreement Extended For Another 50 Years Surf Coast News, Retrieved 28 August 2014
  7. Baker, Richard, 21 March 2011 Alcoa mine could take heritage heathland The Age, Retrieved 28 August 2014
  8. Web site: Victoria - Sulphur dioxide reduction at AWAC . aluminalimited.com . 7 March 2010 . https://web.archive.org/web/20100214134244/http://www.aluminalimited.com/case-studies/ . 14 February 2010 . dead .
  9. Web site: Anglesea. Carbon Monitoring for Action. 23 November 2008.
  10. ABC Radio National Breakfast, 5 July 2012, Anglesea residents worried about Alcoa health impacts Australian Broadcasting Corporation Retrieved 28 August 2014
  11. News: Arup . Tom . Donelly . Beau . Call to clear the air on Anglesea power plant's future . 30 September 2019 . The Age . 19 February 2014.
  12. Taylor, James, Alcoa rejects claim of emission target failure, Surf Coast Times, Retrieved 28 August 2014
  13. Andrew Laird, 17 July 2014, Corporate spin breaks into a trot , Letter to Surf Coast Times reprinted by Surf Coast Air Action. Retrieved 28 August 2014
  14. Friends of the Earth submission on Alcoa power station licence, Retrieved 28 August 2014
  15. John Conroy, 23 May 2014, 'No consultation' over brown coal plant licence, Business Spectator, Retrieved 28 August 2014
  16. News: Taylor, James. 26 July 2014. Anglesea beach sign spells out mine message. Surf Coast Times. Surf Coast Air Action. 28 August 2014. https://web.archive.org/web/20140905213050/http://surfcoast.airaction.org/wp-content/uploads/2014/06/humansign-article-in-surfcoasttimes1.jpg. 5 September 2014. dead.
  17. News: Whitelaw, Anna. 10 August 2014. Hundreds rally for Alcoa coal mine closure. The Age. 28 August 2014 .