Alpaslan-2 Dam | |
Name Official: | Alpaslan-2 Baraji |
Dam Crosses: | Murat River |
Location: | Muş Province |
Dam Type: | Embankment, rock-fill with clay-core |
Dam Length: | 8440NaN0 |
Dam Height: | 1160NaN0 |
Dam Elevation Crest: | 13710NaN0 |
Dam Volume: | 124500000NaN0 |
Spillway Type: | Controlled chute, 6 radial gates |
Spillway Capacity: | 75420NaN0 |
Purpose: | Power, irrigation |
Status: | Operational |
Construction Began: | 2012 |
Opening: | 2021 |
Owner: | Enerjisa Power Generation Inc. |
Res Name: | Alpaslan-2 Reservoir |
Res Capacity Total: | 24310000000NaN0[1] |
Res Elevation: | 13680NaN0 |
Plant Commission: | 2020-2021 |
Plant Turbines: | 2 x 110 MW, 2 x 30 MW Francis-type |
Plant Capacity: | 280 MW |
Plant Annual Gen: | 850 GWh |
Plant Hydraulic Head: | 93.320NaN0 (rated) |
Location Map: | Turkey |
Coordinates: | 39.0353°N 41.5183°W |
Country: | Turkey |
Operator: | Energo-Pro |
The Alpaslan-2 Dam is an embankment dam on the Murat River in Muş Province, Turkey. The dam is located about 32km (20miles) north of the provincial capital, Muş. The primary purpose of the dam is hydroelectric power production and irrigation. Its power station has an installed capacity of 280 MW, planning to deliver 850 GWh annually, and the reservoir will help irrigate 78000ha of land.[2] [3]
Enerjisa Power Generation Inc. acquired the license for the power station from Özışık İnsaat & Enerji in April 2011 and Yenigün Construction started excavating the diversion tunnels May 2012.[4] In late May 2013 Pöyry was awarded the detailed design of the dam, power station, spillway and switch yard.[5]
Enerjisa initially planned the diversion tunnels to be complete by the end of 2012, and the whole project by 2016.[6] Construction progress however has been heavily delayed. Construction was indeed interrupted during a year (2016-2017).
In 2017, after a year of negotiation, the half-built stalled project was transferred to a new contractor, Czech group Energo-Pro (cs), for completion and operation of the dam, with a concession running until 2059.[7] A definitive financing plan was signed as late as November 2019, with Energo-Pro investing a total €175 million.[8]
Alpaslan-2 power station was connected to the grid in November 2020, and fully commissioned in April 2021.[9] [10]