2013 Regina wastewater plant financing referendum explained

A city-wide referendum on a new waste water treatment facility was held in Regina, Saskatchewan on September 25, 2013. The issue of the referendum was whether the facility would be financed through a Public-private partnership (P3) or through the design-bid-build (DBB) approach. The result was 57% against the DBB approach, and the treatment plant ended up being financed by a P3.

Petition

The campaign to call this referendum started in response of a vote by the city council to finance the new $224-million Wastewater plant through a P3. A group called Regina Water Watch was created in opposition to this move, and started collecting signatures to force a referendum on the issue. According to the Saskatchewan Cities Act, a referendum must be held if 10% of the municipality's population sign a petition to hold it. By the end of June 2013, the group had amassed 24,000 signatures, above the 19,310 required by law.[1] However, the city clerk's report judged the petition was insufficient to force the referendum after ruling that over 4000 of the signatures were invalid. The city council decided to vote for the referendum to be held anyway.[2]

Question

The Referendum question was the following:The question used the same wording that the original petition had proposed.

Campaign

The "Yes" side was led by Regina Water Watch, group which self-described as "a citizens’ coalition who are concerned about the privatization of Regina's water and wastewater system". Their coalition "includes community activists, the Council of Canadians Regina Chapter, CUPE 21, Making Peace Vigil and Clean Green Regina".[3] The campaign was also supported by the national Canadian Union of Public Employees (CUPE), which helped organize the group's first meeting.[4] The leader of the campaign was Jim Holmes.

The "No" campaign was run by the City of Regina, and its main leader was Mayor Michael Fougere. The campaign was also supported by the Regina Chamber of Commerce. Federal finance minister Jim Flaherty expressed support for the goal of the campaign in an op-ed entitled "Why I’m giving Regina $58.5 million", in reference to his government's promise of funding part of the costs of the plant if the P3 option was selected.[5]

A debate on the referendum issue was held between Fougere and Holmes on September 18, 2013.[6]

Campaign finance

The City of Regina spent a total of $408,594.96 towards the "No" campaign.[7] Other campaigns and third party groups were not required by law to reveal their campaign expenditures.

The Canadian Union of Public Employees gave significant funds to Regina Water Watch, including registering their domain name reginawaterwatch.com,[8] and paying for the report "Flushing money away: Why the Privatization of Wastewater Treatment Plant is a bad idea", which estimates that a P3 funding scheme would cost the city $61 million more than a DBB.[9] The Regina Chamber of Commerce also participated in the campaign by paying for numerous newspaper and TV ads advocating for the "No side".

During the campaign period, neither CUPE nor the Regina Chamber of Commerce disclosed how much they were spending on the campaign. After the campaign was over, it was revealed that CUPE had spent $180,000 on the "Yes" campaign while the Chamber had spent between $125,000 and $130,000 on the "No" campaign.[10]

Results

2013 Regina Referendum on Wastewater Plant Results[11] !Answer!Votes!Percentage
Yes21,02542.88%
No27,98857.08%
Invalid200,04%
Total49,033100%

Reaction

On the night the Results were posted, Regina Mayor Michael Fougere said ""I'll just say that the people have spoken and the people are always right. I'm very proud of the campaign we ran. I'm proud that people came out in large numbers to express their opinion on a very important issue for our city. I'm very proud of the results."[12]

Jim Holmes reacted to the results by saying "I think we were more optimistic than that going into it. We were up against very tough competition. We were outspent and vilified and everything else."

Aftermath

A P3 model funded the construction of the city's new wastewater treatment plant. In 2015, the Edmonton-based company Epcor was selected to design, build and operate the facility.[13]

By 2016, the facility was nearly built, at a lower than forecasted cost,[14] and it was deemed fully operational by 2018.[15]

External links

Notes and References

  1. Web site: Le collectif Regina Water Watch dépose sa pétition à l'hôtel de ville de Regina. June 20, 2013. ICI.Radio-Canada.ca. fr-ca. 2020-04-03.
  2. Web site: Regina to hold referendum on sewage treatment plant. July 22, 2013. CBC news.
  3. Web site: About us. Regina Water Watch. dead. https://web.archive.org/web/20130731233215/http://reginawaterwatch.ca/about-us/. July 31, 2013.
  4. Web site: L'indépendance de Regina Water Watch mise en doute. July 24, 2013. ICI.Radio-Canada.ca. fr-ca. 2020-04-04.
  5. News: Flaherty. Jim. Why I'm giving Regina $58.5 million. August 16, 2013. The Leader-Post. live. https://web.archive.org/web/20130831194144/http://www.leaderpost.com/news/Flaherty+giving+Regina+million/8798053/story.html. August 31, 2013.
  6. Web site: Few fireworks in waste water treatment plant debate. Global News. en. 2020-04-04.
  7. Web site: Expenditures. Regina.ca.
  8. News: Union, Chamber mum on Regina referendum spending details. September 24, 2013. CBC News.
  9. Web site: Flushing money away: Why the Privatization of Wastewater Treatment Plant is a bad idea. Mackenzie. Hugh. May 6, 2013. cupe.ca.
  10. News: September 27, 2013. Campaign costs revealed in Regina referendum. CBC News. September 1, 2020.
  11. Web site: Wastewater Treatment Plant Referendum September 25, 2013: Official Summary of Results and % Turnout by poll. September 25, 2013. Regina.ca.
  12. News: Referendum results in: P3 model to fund Regina sewage plant. September 25, 2013. CBC News.
  13. Web site: Epcor to operate Regina's wastewater system. The Council of Canadians. 30 May 2014 . en. 2020-04-04.
  14. News: December 20, 2016 . Cost of Regina wastewater plant comes in $6M less than expected .
  15. Web site: Schick . Lisa . Construction troubles plagued Regina’s wastewater treatment plant . 2023-11-12 . 980 CJME . en.