Çetin Dam Explained

Çetin Dam
Location Map:Turkey
Coordinates:37.9742°N 42.3783°W
Country:Turkey
Location:Pervari and Şirvan discticts, Siirt Province
Purpose:Power
Status:O
Construction Began:December 2011
Opening:May 2020[1]
Cost:US$678 million
Dam Type:Embankment, roller-compacted concrete
Dam Height Thalweg:143 m
Dam Height Foundation:165 m
Dam Length:492 m
Dam Width Crest:10 m
Dam Volume:4 726 527 m3
Dam Elevation Crest:825 m
Dam Crosses:Botan River
Res Capacity Total:615 million m3
Res Surface:100NaN0
Res Max Length:37 km
Plant Hydraulic Head:1400NaN0
Plant Commission:May 2020
Plant Turbines:3 x 135 MW + 1 x 15 MW Francis-type
Plant Capacity:420
Plant Annual Gen:1175

The Çetin Dam hydropower dam, on the Botan River in Siirt Province, Turkey, with an installed capacity of 420 MW. It was completed in 2020.[2]

Location

The dam will be located directly downstream of the Botan and Büyük River confluence. Also part of the Çetin project is a smaller dam 60NaN0 downstream with 450NaN0 in height. The Çetin lower dam will regulate outflows from the Çetin main dam and also produce hydroelectric power with a 112 MW capacity via two 56 MW Kaplan turbines.

Overall, six dams are to be built on the Botan River, among which Çetin dam will have the largest power plant.

Design

Çetin Dam is a roller-compacted concrete body embankment dam. With a volume exceeding 4.7 million m3, il will be the biggest of its kind in Turkey, and bigger than any existing RCC dam in Europe. The dam will be 165 m high and create a 615 million m3 reservoir.[3]

The dam's power plant will house four vertical axis Francis turbine-generators, three of them with a 135 MW capacity and a smaller 15 MW one.[4]

Funding

The owner was the Norwegian, Statkraft, at a cost of US $678 million. The Contractor was Yϋksel-iLci Joint Venture. Veidekke Industri AS was the subcontractor for Cetin dam. In September 2017, Limak invested $400 million to purchase the rights, in order to complete the whole project by 2020–21.[5] [6]

Timeline

Construction on the main dam began in December 2011 and the power plant was first expected to be complete in 2015, with a planned capacity of 401 MW.[7]

The project experienced delays due to Kurdistan Workers' Party attacks on the construction site and equipment. In February 2016, Statkraft suspended construction.[8] Works resumed in July 2017.[9]

Construction was 84% complete as of September 2019 ; at that time, as many as 15,000 m3 of concrete are poured onto the structure every day.

The dam started impounding water in January 2020. The first two units of the power station started generating electricity in April 2020, whereas the two remaining ones are expected to be commissioned by May 2020.

See also

Notes and References

  1. Web site: Southeastern Turkey's new dam begins producing energy, adds $73.8M to economy. DAILY. SABAH. May 27, 2020. Daily Sabah.
  2. Web site: Çetin Dam and Hydroelectric Power Plant Started Energy Production. 13 April 2020. raillynews.com. 2020-04-26.
  3. Web site: WHEN COMPLETED, IT WOULD BE THE BIGGEST IN TURKEY AND EUROPE. 16 September 2019. www.tarimorman.gov.tr. 2020-04-26.
  4. Web site: Çetin Dam begins to impound the waters of the Botan River in southeast of Turkey. 9 January 2020. Doğruhaber Gazetesi. 2020-04-26.
  5. Web site: Statkraft sells Cetin project to Turkish firm. 22 September 2019. hydroreview.com.
  6. Web site: Limak Energy Group has purchased the Cetin Dam and Hydroelectric Power. 25 September 2019. PressReader.
  7. News: Norway's Statkraft to build 517-MW Cetin in Turkey. 19 October 2012. Hydro World. 28 September 2011.
  8. News: Norway's Statkraft in the HES 'Cetin arrived. 24 February 2016. Vatan. 5 February 2016. tr.
  9. Web site: The Construction of Çetin Dam and Hydroelectric Power Plant.... 12 April 2020. EnerjiEkonomisi. 2020-04-26.